Banner provided the planning/design/construction phase services for the original Aberdeen WWTF.  Changing permit conditions and aging equipment necessitated the phased upgrades.  Major project components for the Phase I Improvements included replacement of 6 screw pumps, pretreatment equipment replacement, BioFilter equipment replacement, construction of 4 new aeration basins with new new blower building and blowers, replacement of 2 final clarifier mechanisms, and UV disinfection equipment replacement.  Major improvements for the Phase IIA project included a new chemical feed building and equipment and process monitoring and control system.  Major improvements for the Phase IIB project included the addtion of Dissolved Air Flotation (DAF) process, replacement of 2 primary clarifier mechanisms, as well as replacement of boiler/heat exchanger equipment, pipes and valves, and sludge pumps in the digester process.  In addition, improvements were made to provide asphalt paving of the City's equalization basins.

Checkmark Icon

Project Goal #1

Complete the improvements while staying completely operational

Checkmark Icon

Project Goal #2

Address concerns with aging equipment 

Checkmark Icon

Project Goal #3

Plan for compliance with new permit limits

Checkmark Icon

Project Goal #4

Plan for future improvements to accommodate future nutrient removal requirements

Project Features

  • Additional aeration basins and upgraded final clarifiers
  • New screening, grit removal, and comminutor equipment
  • New screw pumps at main lift station and at the wastewater treatment plant

Services Provided

  • Final Design
  • Construction Documents
  • Bidding Services
  • Construction Administration, Staking and Observation
  • Operations and Maintenance Manual