Ivanhoe Utility Improvements

Ivanhoe Utility Improvements

Location

Ivanhoe, MN

Previous Next

Excessive inflow and infiltration (I/I) in the gravity sewer collection system was causing hydraulic overloading of the wastewater treatment system in the City of Ivanhoe. Several point repairs were performed to fix some of the known I/I sources. However, the repairs were not reducing I/I enough for the community to consistently meet their discharge permit. The City enlisted Banner’s expertise to perform an I/I investigation, including inventory and analysis of the current collection system pipe material and age, review of televising records, and identification of sump pump and roof drain connections.

The recommended improvements included a combination of traditional open-cut and trenchless construction methods. The project also incorporated water distribution system and storm drainage improvements. The trenchless construction methods were recommended in areas where these systems did not require upgrades and the pavement was in good condition, minimizing street repairs. This allowed the City to focus their efforts on wastewater collection system improvements. The project was completed in the following two phases:

Bid Schedule No. 1: Open-cut pipe replacement for the gravity sewer mains.  Replacement of the 4" service lines connecting residences or businesses to the sewer main were integrated into the project. Water distribution system and storm drainage improvements were also incorporated into the improvements.

Bid Schedule No. 2: Trenchless construction using Cured-In-Place Pipe (CIPP) for both sewer main and lateral rehabilitation. This new technology for lining the services was implemented to benefit the residents of Ivanhoe through a generous grant. The project further reduced infiltration of groundwater into the sanitary sewer system.

Checkmark Icon

Project Goal #1

Reduce hydraulic overloading (I/I) of the wastewater treatment facility

Checkmark Icon

Project Goal #2

Utilize trenchless construction methods to maximize the funds directed to upgrading the wastewater collection system

Project Features

  • Sanitary Sewer Main Collection Lines - CIPP
  • Sanitary Sewer Lateral Connections - CIPP
  • Sanitary Sewer Laterals to ROW - CIPP

Services Provided

  • Facility Plan
  • Wastewater Collection Main Line Evaluation
  • Preliminary/Final Design
  • Construction Documents
  • Bidding Services
  • Construction Contract Administration
  • Construction Staking and Observation