Volga Wastewater Treatment Facility Improvements - 2018
- BAI Number
- 22599.00.00
- Project Bid Date:
- 08/14/2018 2:00 PM CST
- Project Bid Location:
- Volga City Hall, Finance Officer, 226 Kasan Avenue, Volga, SD 57071
Bid Schedule(s)
- Bid Schedule1
- Lump Sum Bid Schedule
- Probable Cost 1
- to $2,349,600.00
Scope of Work 1
Construct new wastewater Pretreatment Building with screen, washer and compactor equipment as well as a lab, restroom and office area;
Construct new structure for UV disinfection system, and provide and install new UV disinfection equipment;
Improvements to existing Blower Building, including new blower motors and new roof;
Mechanical work at Pretreatment Building and Blower Building;
Electrical work at Pretreatment Building, Blower Building, and UV Structure;
Improvements to the wetland inlet piping;
Site grading and utilities;
All other miscellaneous work required not herein mentioned, but inferred from the construction contact documents.
Addendum Dates
- 08/03/2018 Memo Faxed - Click here to download
- 08/10/2018 Memo Faxed - Click here to download
- 08/13/2018 Memo Faxed - Click here to download
Additional Files
- Soils Report Dated February 16, 2018 (07/18/2018)
Contact Persons:
- General, Demolition, and Site Piping - Tanya Miller - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Civil - Neil Eichstadt - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Process Control and Instrumentation - Dennis Rebelein - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Structural - Adam Hanson - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Electrical - Michael Fisher, West Plains Engineering, (605) 362-3753
- Mechanical - Isaac Anderson. PE - email, West Plains Engineering, (605) 362-3753
- Contact us about this project