Vermillion Ground Storage Reservoir Improvements - 2019
- BAI Number
- #22937.00.00
- Project Bid Date:
- 06/25/2019 10:00 AM CST
- Project Bid Location:
- City Engineer, Vermillion City Hall, 25 Center Street, Vermillion, SD 57069
Bid Schedule(s)
- Bid Schedule1
- Lump Sum Bid Schedule
- Probable Cost 1
- $350,000 to $400,000
Project Deadlines 1
- Substantial Completion
- 06/26/2020
- Final Completion
- 07/31/2020
Scope of Work 1
Base Bid:
Surface preparation and recoating of carbon steel ground storage reservoir interior roof. Interior roof shall be abrasive blasted and completely coated with zinc-rich primer and two coats of epoxy, a stripe coat of epoxy shall be applied after primer. Reservoir is 90’-8” inside diameter and a 33’-0” side wall height.
Bid Alternate #1:
Surface preparation and recoating of carbon steel ground storage reservoir interior walls and floor. Interior walls and floor shall be abrasive blasted and completely coated with zinc-rich primer and two coats of epoxy, a stripe coat of epoxy shall be applied after primer. Reservoir is 90’-8” inside diameter and a 33’-0” side wall height.
Addendum Dates
No Addendums
Contact Persons:
- Structural - Adam Hanson - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Contact us about this project