Project Information

Vermillion Ground Storage Reservoir Improvements - 2019

BAI Number
#22937.00.00
Project Bid Date:
06/25/2019 10:00 AM CST
Project Bid Location:
City Engineer, Vermillion City Hall, 25 Center Street, Vermillion, SD 57069

Bid Schedule(s)

Bid Schedule1
Lump Sum Bid Schedule
Probable Cost 1
$350,000 to $400,000

Project Deadlines 1

Substantial Completion
06/26/2020
Final Completion
07/31/2020

Scope of Work 1

Base Bid:

Surface preparation and recoating of carbon steel ground storage reservoir interior roof. Interior roof shall be abrasive blasted and completely coated with zinc-rich primer and two coats of epoxy, a stripe coat of epoxy shall be applied after primer. Reservoir is 90’-8” inside diameter and a 33’-0” side wall height.

Bid Alternate #1:

Surface preparation and recoating of carbon steel ground storage reservoir interior walls and floor. Interior walls and floor shall be abrasive blasted and completely coated with zinc-rich primer and two coats of epoxy, a stripe coat of epoxy shall be applied after primer. Reservoir is 90’-8” inside diameter and a 33’-0” side wall height.

Addendum Dates

No Addendums

Contact Persons: