Bid Letting Information
Banner Associates, Inc.
409 22nd Avenue South
PO Box 298
Brookings, SD 57006
Phone: (605) 692-6342
Fax: (605) 692-5714
www.BannerAssociates.com
Lewis & Clark Regional Water System - Madison Reservoir
Project number: 20000.39.01
- Pre-Bid Meeting Date:
- 06/17/2022 10:00 AM
- Pre-Bid Meeting Location:
- Lewis & Clark Regional Water System, 46986 Monty Street, Tea, SD 57064
- Project Bid Date:
- 06/28/2022 1:00 PM
- Project Bid Location:
- Lewis & Clark Regional Water System Office, 46986 Monty Street, Tea, SD 57064
Bid Schedule(s)
Project Deadlines 1
- Substantial Completion
- 08/23/2024
- Final Completion
- 10/11/2024
Scope of Work 1
A 1.0 million gallon prestressed concrete (AWWA D110, Type III) ground storage reservoir with a height to overflow of 56 feet, including a mixing system.
Excavation of existing subgrade and replacement with engineered fill for the reservoir floor and foundation.
Interior reservoir piping and all necessary fittings.
Construction of a buried concrete vault and installation of isolation valves.
Site piping including concrete encased 16-inch pressure piping, isolation, and blow-off valves.
Site concrete structures including concrete headwalls and energy dissipating structures.
Installation of telemetry and control equipment and instrumentation.
Site work including installation of power, generator, all excavation and finish grading for construction of the reservoir, storm water detention facility, access entrances and concrete driveway, storm water piping, fences and gates, and site topsoiling, seeding, and restoration.
Reservoir water tightness testing and disinfection.
Pipeline hydrostatic pressure testing and disinfection.
Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction Contract Documents.
Addendum Dates
- 06/07/2022 Emailed - Click here to download
- 06/23/2022 Emailed - Click here to download
Additional Files
- Geotechnical Report (06/01/2022)
- Phase 1 Site Assessment (06/01/2022)
Contact Persons:
- Process - Jared Larson, Banner Associates, Inc. , 605-692-6342 or 1-855-323-6342, jaredl@bannerassociates.com
- Structural - Adam Hanson, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;, adamh@bannerassociates.com
- Tim Conner, Banner Associates, Inc., (605) 692-6342 or 1-855-323-6342;, timc@bannerassociates.com
- Electrical - Michael Fisher, West Plains Engineering, (605) 362-3753,
- Mechanical - Connor Swiontek, West Plains Engineering, (605) 362-3753, connor.swiontek@WestPlainsEngineering.com
Banner Associates, Inc.
409 22nd Avenue South
PO Box 298
Brookings, SD 57006
Phone: (605) 692-6342
Fax: (605) 692-5714
www.BannerAssociates.com
Project number: 20000.39.01
A 1.0 million gallon prestressed concrete (AWWA D110, Type III) ground storage reservoir with a height to overflow of 56 feet, including a mixing system.
Excavation of existing subgrade and replacement with engineered fill for the reservoir floor and foundation.
Interior reservoir piping and all necessary fittings.
Construction of a buried concrete vault and installation of isolation valves.
Site piping including concrete encased 16-inch pressure piping, isolation, and blow-off valves.
Site concrete structures including concrete headwalls and energy dissipating structures.
Installation of telemetry and control equipment and instrumentation.
Site work including installation of power, generator, all excavation and finish grading for construction of the reservoir, storm water detention facility, access entrances and concrete driveway, storm water piping, fences and gates, and site topsoiling, seeding, and restoration.
Reservoir water tightness testing and disinfection.
Pipeline hydrostatic pressure testing and disinfection.
Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction Contract Documents.