Lewis & Clark Regional Water System - Hull Pump Station & Sheldon Meter Building

BAI Number
20000.49.
Pre-Bid Meeting Date:
07/26/2022 2:00 PM
Pre-Bid Meeting Location:
Lewis & Clark Regional Water System, 46986 Monty Street, Tea, SD 57064
Project Bid Date:
08/09/2022 2:00 PM
Project Bid Location:
Lewis & Clark Regional Water System Office, 46986 Monty Street, Tea, SD 57064

Bid Schedule(s)

Bid Schedule1
Lump Sum Bid Schedule
Probable Cost 1
3,000,000.00 to $3,500,000.00

Project Deadlines 1

Scope of Work 1

Hull Pump Station.  New pump station located south of the intersection of 340th St and Harrison Ave.  Outside dimensions are 30’-8”x68’-8”.
Sheldon Meter Building.  New meter building located at the site of Sheldon’s water treatment plant at 600 N 2nd Ave.  Outside dimensions are 22’x36’.
The work includes all piping, fittings, pumps, motors, VFDs, meters, gauges, valves, and appurtenances including but not limited to isolation valves, control valves, combination air valves, check valves, chemical feed and storage systems and telemetry & control systems as required at each location.
The work includes all electrical and mechanical equipment and systems, including generators.
Site work includes, but is not limited to:

                     -Excavation, fill, grading, lighting, utilities, access road construction, parking area, fencing and site topsoiling, seeding and restoration.
                     -Ductile iron site piping connections on inlet and outlet sides of the buildings including corrosion protection (galvanic anodes).
                     -Sanitary sewer piping and connections to septic systems.

Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction contract documents.   

 

 

The Work will be substantially complete on or before October 27, 2023 (including Bid Alternate 1, if awarded), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before  December 15, 2023 (including Bid Alternate 1, if awarded)  .

Addendum Dates

Additional Files

Contact Persons:

  • Process - Bryan Lipp - email, Banner Associates, Inc. (Brookings Office), (605) 692-6342 or 1-855-323-6342
  • Structural - Adam Hanson - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Architectural - Dave Lorang - email, Banner Associates.Inc. , (605) 692-6342 or 1-855-323-6342; cell # (605) 929-5554
  • Electrical - Todd Weidner PE - email, West Plains Engineering, 605-306-8092
  • Mechanical - Connor Swiontek - email, West Plains Engineering, 605-306-8035
  • Contact us about this project