Project Information

Lake Preston Water Distribution Improvements - Elevated Water Tower

BAI Number
22886.00.16
Pre-Bid Meeting Date:
12/01/2021 2:00 PM
Pre-Bid Meeting Location:
Lake Preston City Office, 111 3rd Street NE, Lake Preston, SD 57249
Project Bid Date:
12/08/2021 2:00 PM
Project Bid Location:
Lake Preston City Office, 111 3rd Street NE, Lake Preston, SD 57249

Bid Schedule(s)

Project Deadlines 1

Substantial Completion
05/01/2023
Final Completion
07/01/2023

Scope of Work 1

A 100,000 Gallon elevated water tower with a height to overflow of 154 feet and all piping, fittings, appurtenances and valves.  The ground floor of the tower will be used as a storage facility and control room;
Demolition and removal of existing water tower, foundation and existing apparatuses;
Site work, yard piping, energy dissipation structure, concrete driveway and landscaping rock;
All mechanical, electrical and control equipment necessary to provide a fully functioning facility;
Corrosion protection system components including coatings, linings, and cathodic protection systems;
Temporary and permanent erosion control, reclamation and seeding;
Traffic control and haul road maintenance during construction;
Reservoir and pipeline cleaning, flushing, hydrostatic pressure testing and disinfection;
Hydrodynamic mixing system; and
Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction Contract Documents.

Addendum Dates

Additional Files

Contact Persons:

  • Process - Jared Larson - email, Banner Associates, Inc. , 605-692-6342 or 1-855-323-6342
  • Structural - Adam Hanson - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Civil - Beth Niemeyer - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Electrical - Jeremy Nelson - email, Power System Engineering, Inc. , (320) 978-8041
  • Mechanical - Charles DeBerg - email, Power System Engineering, Inc. , (320) 978-8041
  • Contact us about this project