Lake Preston Water and Wastewater Improvements Phase 1 & SDDOT Park Avenue Street Improvements
- BAI Number
- 22886.00
- Project Bid Date:
- 12/15/2021 2:00 PM
- Project Bid Location:
- Lake Preston City Office, 111 3rd Street NE, Lake Preston, SD 57249
Bid Schedule(s)
Scope of Work 1
SCHEDULE 1
Opinion of Construction Costs: $6,500,000 - $7,000,000
Interim Completion Dates
October 15, 2022
Substantial Completion Date
October 15, 2023
Final Completion Date
December 1, 2023
Scope:
Furnish and Install approximately 2,325 LF of 8” diameter and 10,790 LF of 6” diameter water main and associated service lines;
Furnish and Install approximately 2,360 LF of 12” diameter, 400 LF of 10” diameter, 7,380 LF of 8” diameter and 3,980 LF of 4” diameter gravity sewer with associated service lines;
Furnish and Install approximately 110 LF of Bore and Jack 16” Steel Casing Pipe
Furnish and Install approximately 50 LF of Bore and Jack 24” Steel Casing Pipe
Furnish and Install approximately 2,400 LF of RCP storm sewer;
Furnish and Install water tracer wire systems;
Furnish and Install junction boxes, manholes, valves and appurtenances;
Approximately 27,850 SY of full depth roadway reclamation;
Furnish and Install approximately 13,815 SY of geotextile fabric for subgrade stabilization;
Furnish and Install approximately 291,719 SF of Cement treated subgrade stabilization;
Furnish and Install approximately 18,030 Tons of base course;
Furnish and Install approximately 27,340 SY of asphalt concrete;
Furnish and Install approximately 760 SY of PCC approach pavement;
Furnish and Install approximately 8,750 LF of concrete curb & gutter;
Furnish and install approximately 13,835 SF of concrete sidewalk;
Surface restoration and all other miscellaneous work required not herein mentioned, but inferred from the construction Contract Documents.
SCHEDULE 2
Opinion of Construction Costs: $350,000 - $380,000
Substantial Completion Date
October 15, 2022
Final Completion Date
November 15, 2022
Scope:
Furnish and Install approximately 2,100 LF of 8-inch CIPP;
Furnish and Install approximately 870 LF of 10-inch CIPP;
Furnish and Install approximately 26 CIPP sanitary service connection;
Furnish and Install approximately 980 LF CIPP lateral lining of varying sizes – 4” and 6”;
Furnish and Install approximately 76 VF of manhole lining;
Furnish and Install approximately 3 sanitary sewer manholes;
Surface restoration and all other miscellaneous work required not herein mentioned but inferred from the construction Contract Documents.
Addendum Dates
- 12/10/2021 Emailed - Click here to download
- 12/14/2021 Emailed - Click here to download
Additional Files
- Soils Report (11/30/2021)
Contact Persons:
- Civil - Weston Blasius - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Contact us about this project