Lake Norden Wellfield and Raw Water Transmission - 2019 Bid Package #2
Project number: 22720.00.00
- Project Bid Date:
- 04/18/2019 2:00 PM CDT
- Project Bid Location:
- City of Lake Norden, Finance Officer, PO Box 213, Lake Norden, SD 57248
Bid Schedule(s)
- Type 1
- Lump Sum Bid Schedule
- Probable Cost 1
- $530,000 to $630,000
Project Deadlines 1
- Substantial Completion
- 09/27/2019
- Final Completion
- 11/15/2019
Scope of Work 1
Installation of approximately 7,800 L.F. conventional open cut buried 10” diameter raw water transmission pipe between the Water Treatment Plant and the new wells.
Installation of approximately 430 L.F. conventional open cut buried 6” diameter raw water pipe from new transmission pipe to wells. Installation of valve pits, column pipes, well pumps, motors and pitless adaptors and appurtenances for three new wells.
Installation of 90 L.F of directionally drilled 24” steel casing pipe and 10” carrier pipe.
Installation of 510 L.F. directionally bored 10” diameter raw water transmission pipe at paved road, highway and creek crossings.
Connection to and completion of construction of three new wells, including installation of pumps, and pitless adaptors.
Addendum Dates
- 04/15/2019 Memo Faxed - Click here to download
Contact Persons:
Banner Associates, Inc.
409 22nd Avenue South
PO Box 298
Brookings, SD 57006
Phone: (605) 692-6342
Fax: (605) 692-5714
www.BannerAssociates.com
Project number: 22720.00.00
Installation of approximately 7,800 L.F. conventional open cut buried 10” diameter raw water transmission pipe between the Water Treatment Plant and the new wells.
Installation of approximately 430 L.F. conventional open cut buried 6” diameter raw water pipe from new transmission pipe to wells. Installation of valve pits, column pipes, well pumps, motors and pitless adaptors and appurtenances for three new wells.
Installation of 90 L.F of directionally drilled 24” steel casing pipe and 10” carrier pipe.
Installation of 510 L.F. directionally bored 10” diameter raw water transmission pipe at paved road, highway and creek crossings.
Connection to and completion of construction of three new wells, including installation of pumps, and pitless adaptors.