Harrisburg Westside Sanitary Sewer Improvements - Phase 1
- BAI Number
- 23453.00
- Project Bid Date:
- 10/19/2022 2:00 PM
- Project Bid Location:
- Harrisburg City Hall, 301 E Willow Street, Harrisburg, SD 57032
Bid Schedule(s)
- Bid Schedule1
- Lump Sum Bid Schedule
- Probable Cost 1
- $7,375,000 to $8,250,000
Project Deadlines 1
- Substantial Completion
- 12/01/2023
- Final Completion
- 06/01/2024
Scope of Work 1
Sanitary sewer installation for the City of Harrisburg including 5,680 feet of 24” sanitary sewer piping, 1,850 feet of 30” sanitary sewer piping, and 2,480 feet of 36” sanitary sewer piping as well as large diameter manholes. Project work includes the removal and replacement of existing gravel, asphalt and walking path surfacing, removal and replacement of concrete curb and gutter, crop field restoration, lift station demolition, removal and replacement of a storm sewer inlet and excavating for installation of sanitary sewer improvements.
Addendum Dates
- 10/12/2022 Emailed - Click here to download
- 10/17/2022 Emailed - Click here to download
Additional Files
- Geotechnical Report (09/28/2022)
- SUE Report for Gas Mains (09/28/2022)
- Record Drawings for WW Treatment Improvements Phase I - Gravity Sewer & Lift Station (Main Lift Station) (09/28/2022)
- Development Plans North of Honeysuckle LS (South Parcel) (09/28/2022)
- Development Plans North of Honeysuckle LS (North Parcel) (09/28/2022)
Contact Persons:
- General, Demolition, and Site Piping - Tanya Miller - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Civil - Alex Welbig - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
- Contact us about this project