Clark Rural Water System – Bradley and Willow Lake Improvements
- BAI Number
- 22825.00.00
- Project Bid Date:
- 05/10/2019 11:00 AM CST
- Project Bid Location:
- Clark Rural Water System, 1001 1st Avenue W., Clark, SD 57225
Bid Schedule(s)
- Bid Schedule1
- Unit Price Bid Schedule
- Probable Cost 1
- $1,500,000 to $1,700,000
Project Deadlines 1
- Substantial Completion
- 11/01/2019
- Final Completion
- 12/01/2019
Scope of Work 1
Base Bid:
- Construction of approximately 61,600 linear feet of 6-inch diameter water main;
- Construction of approximately 31,700 linear feet of 8-inch diameter water main;
- Furnish and installation of necessary valves, fittings, joint restraints and concrete thrust blocks to provide a complete and functioning potable water main;
- Furnish, transport and install a pre-fabricated concrete meter pit near Willow Lake, SD with all mechanical, electrical and control equipment necessary to provide a fully functioning facility, including interior piping and valves, and control systems integration with the City of Willow Lake’s control system;
- Temporary and permanent erosion control, reclamation and seeding;
- Water main flushing, hydrostatic pressure testing and disinfection; and
- Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction Contract Documents.
Bid Alternate #1:
- Construction of approximately 5,100 linear feet of 10-inch diameter water main; and
- Furnish and installation of necessary valves, fittings, joint restraints and concrete thrust blocks to provide a complete and functioning potable water main.
Addendum Dates
- 05/07/2019 Memo Faxed - Click here to download
Contact Persons:
- Process - Bryan Lipp - email, Banner Associates, Inc. (Brookings Office), (605) 692-6342 or 1-855-323-6342
- Ben Meyer - email, Banner Associates, 605-692-6342
- Contact us about this project