Project Information

Aurora-Brule Rural Water System - Water Treatment Plant Improvements -2020

BAI Number
22821.00.00
Project Bid Date:
04/10/2020 11:00 AM CDT
Project Bid Location:
Aurora-Brule Rural Water System, Inc., 117 2nd Street, Kimball, SD 57355

Bid Schedule(s)

Bid Schedule1
Lump Sum Bid Schedule
Probable Cost 1
$350,000 to $400,000

Project Deadlines 1

Substantial Completion
11/30/2020
Final Completion
12/31/2020

Scope of Work 1

Demolition of three (3) high service pumps, four (4) variable frequency drives (VFDs), air compressor, process piping components, and other miscellaneous items;
Furnish and install new 50 Hp high service pump and VFD;
Furnish and install two (2) new 150 Hp high service pump and VFDs;
Install new 75 Hp backwash pump VFD;
Installation of new air compressor;
Installation of new pressure relief valve, air release valves, and other process piping components; and
Clean up, startup services, and all other miscellaneous work required but not herein mentioned but inferred from the construction Contract Documents.

In addition, a Bid Alternate (Bid Alternate #1) with the following scope:

Furnish spare 75 Hp backwash pump assembly.

Addendum Dates

Contact Persons:

  • Process - Bryan Lipp - email, Banner Associates, Inc. (Brookings Office), (605) 692-6342 or 1-855-323-6342
  • Electrical Designer -Todd Baack - email, West Plains Engineering, (605) 362-3753
  • Contact us about this project