Project Information

University of South Dakota Burgess/ Norton Parking Lot 5 Expansion

BAI Number
#22940.00.00 OSE# R0619--16X
Pre-Bid Meeting Date:
04/09/2019 11:00 AM CST
Pre-Bid Meeting Location:
University of South Dakota, Service Center, Conference Room 105
Project Bid Date:
04/16/2019 3:00 PM CST
Project Bid Location:
Office of the State Engineer, Joe Foss Building, 523 Capitol, Pierre, SD 57501-3182

Bid Schedule(s)

Project Deadlines 1

Substantial Completion
08/16/2019
Final Completion
08/23/2019

Scope of Work 1

BASE BID - Probable Cost: $850,000 to 900,000

Approximately 4,000 CuYd of Unclassified Excavation;

Approximately 72,000 SqFt of Cement Treated Subgrade;

Installation of approximately 1,800 tons of gravel base course and 6,800 SqYd of 5” Portland Cement Concrete pavement;

Installation of approximately 1,100 LF of concrete curb and gutter and 8,000 SqFt of concrete flatwork;

Installation of approximately 275 LF of storm sewer pipe and associated drop inlets and manholes;

Associated topsoil placement, erosion control, pavement markings, removals and traffic control; and

Electrical site improvements including parking lot lighting.

BID ALTERNATE #1  - Probable Cost: $10,000 to $15,000

a.       Install approximately 1,700 SqFt of concrete sidewalk

BID ALTERNATE #2 - - Probable Cost: $12,000 to $17,000

a.       Remove approximately 225 SqYd of concrete sidewalk

b.       Install approximately 2,000 SqFt of concrete sidewalk

Addendum Dates

Contact Persons:

  • Civil - Rich Uckert - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Civil - Neil Eichstadt - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Electrical - Kelly Loudenslager, Associated Consulting Engineering, Inc. , (605) 335-3720
  • Contact us about this project