TM Rural Water System Highway 18 Waterline Relocation Project System Improvements - 2017
- BAI Number
- #22659.00.00
- Project Bid Date:
- 09/25/2017 2:00 PM CDT
- Project Bid Location:
- TM Rural Water District, 110 North Main, Parker, SD 57053
Bid Schedule(s)
- Bid Schedule1
- Unit Price Bid Schedule
- Probable Cost 1
- $500,000 to $650,000
- Bid Schedule2
- Unit Price Bid Schedule
- Probable Cost 2
- $80,000 to $120,000
Project Deadlines 1
- Substantial Completion
- 06/15/2018
- Final Completion
- 07/31/2018
Scope of Work 1
Project scope of work for Bid Schedule No.1 will include the following:
Approximately 22,100 feet of 6-inch and 11,000 feet of 2.5-inch SDR-21 ASTM Class 200 PVC pipe.
Approximately 2,600 feet of directional boring with various pipe sizes including 3-inch, 6-inch and 8-inch pipe.
All necessary materials and labor needed to complete the project, including but not limited to piping, fittings, valves, meters, disinfection, pressure testing and associated sampling.
Work will include disconnecting and reconnecting approximately 16 existing customer.
Cropland, grass land, residential seeding, compliance with the storm water pollution prevention plan (SWPPP) and all necessary erosion control practices to maintain and restore the project site.
Project scope of work for Bid Schedule No.2 will include the following:
Approximately 3,000 feet of 1.5-inch SDR-21 ASTM Class 200 PVC pipe.
Approximately 600 feet of directional boring with various pipe sizes including 3-inch and 8-inch pipe.
Work will include boring under Highway 18 to obtain additional depth and connecting to existing pipe. Pipe sizes for these connections are 1.5-inch, 6-inch and 8-inch pipe.
All necessary materials and labor needed to complete the project, including but not limited to piping, fittings, valves, meters, disinfection, pressure testing and associated sampling.
Addendum Dates
- 09/21/2017 Faxed - Click here to download
- 09/22/2017 Memo Faxed - Click here to download