Project Information

Lewis and Clark Regional Water System – Lime Sludge Drying Bed Maintenance - Middle Bed

BAI Number
21580.10.00
Pre-Bid Meeting Date:
09/17/2020 2:00 PM CDT
Pre-Bid Meeting Location:
Lewis & Clark Regional Water System Water Treatment Plant, North of Vermillion, SD at 31474 SD Highway 19, Vermillion, SD 57069
Project Bid Date:
09/22/2020 2:00 PM CDT
Project Bid Location:
Lewis & Clark Regional Water System Water Treatment Plant, North of Vermillion, SD at 31474 SD Highway 19, Vermillion, SD 57069

Bid Schedule(s)

Bid Schedule1
Probable Cost 1
to

Project Deadlines 1

Substantial Completion
09/01/2021
Final Completion
10/01/2021

Scope of Work 1

BASE BID PROBABLE COST - $400,000

ALTERNATE BID PROBABLE COST - $22,000

BASE BID

  • 6,199 CY of unclassified excavation and digout excavation.
  • 4,890 CY of scarify and re-compact existing subgrade.
  • 47,062 tons of imported clay material to construct drying bed liner and access ramps.
  • 525 tons of aggregate surfacing.
  • 1,843 LF of 6” drain pipe and associated bedding and drainage fabric.
  • Construct a vehicle construction entrance.
  • 806 CY of Topsoil Placement
  • One acre of reclamation and seeding.
  • 2,500 SY of erosion control blanket.
  • 3,880 tons of Remove and Stockpile Lime Sludge (Alternate 1)
  • Clean-up and all other miscellaneous work required, not herein mentioned, but inferred from the construction Contract Documents

ALTERNATE BID 

  • 3,880 tons of Remove and Stockpile Lime Sludge (Alternate 1)
  • Cleanup and all other miscellaneous work required, not herein mentioned but inferred for the construction Contract Documents. 

Addendum Dates

Additional Files

Contact Persons:

  • Civil - Weston Blasius - email, Banner Associates, Inc. , (605) 692-6342 or 1-855-323-6342;
  • Tim Conner - email, Banner Associates, Inc., (605) 692-6342 or 1-855-323-6342;
  • Contact us about this project