Project Information

Clear Lake Community Access Street Reconstruction

BAI Number
23006.00.00
Project Bid Date:
04/01/2020 11:00 AM CST
Project Bid Location:
City of Clear Lake, Finance Officer, PO Box 107, 125 3rd Avenue South, Clear Lake, SD 57226-0107

Bid Schedule(s)

Bid Schedule1
Lump Sum Bid Schedule
Probable Cost 1
$625,000 to $675,000

Project Deadlines 1

Substantial Completion
10/02/2020
Final Completion
10/16/2020

Scope of Work 1

Furnish and Install approximately 840 LF of 24” diameter/ 18”RC storm sewer pipe along with 7 storm inlets;
Furnish and Install approximately 2,040 LF of concrete gutter/ curb and gutter;
Approximately 3 blocks of street reconstruction and surface restoration.